Wellings Reserve Upgrade Project
November 2023 Forwarde Group successfully achieved the completion of the Wellings Reserve Upgrade Project.
The upgrade project required:
​
-
Site preparation
-
Earthworks
-
Excavate area for precast dish drain
-
Install geograb & aggregate
-
Pour concrete blinding layer
-
Install precast dish drain
-
Install stormwater pipes & pits
-
FRP in-situ V drains
-
Excavate area for flush kerb
-
FRP flush kerb
-
Demobilistaion
-
Site handover
​​